| Church | Christ Church Highbury, 159 Highbury Grove, London, N5 1SA |
| Cloudesley grant | SCBP grant April 2024: £10,000 |
| Total cost | £8,872 – the underspend on the grant was written back to Cloudesley. |
| Background |
Christ Church undertook the following work:
|
| Challenges/Learning | They were unable to install Quattroseal around the external door frames as they were advised that the stone around the door frame was too porous. |
| Contractors used |
|
| Impact of the SCBP/Inspired Efficiency | The project enabled Christ Church to revisit their second energy report and see if any further improvements could be made in the efficiency of the building. They found that meeting with the Inspired Efficiency team enabled them to see what areas were realistic to focus on for the purpose of this grant. Without the SCBP, they feel that it is unlikely that they would have had these works carried out at this point as there are other building works that would have taken precedence. |